Project portfolio
TOURISM - ALL LOCATIONS
Milford Visitor Centre
This project involved the construction of the two new double leveled wings at either end of the existing Milford Sound Visitor Centre. The remote location and extreme weather conditions of the site required extensive logistical co-ordination to ensure that materials and manpower were on site as and when required. The existing Visitor Centre, which has around 2000 visitors through its doors per day, also had to be kept fully operational at all times. The building was of concrete floor and steel framed construction with aluminium cladding to the exterior.
CONTRACT VALUE: $2,120,000
CONTRACT PERIOD: 38 weeks
CLIENT: Milford Sound Development Authority
PROJECT MANAGER: McCulloch Architects Ltd
ARCHITECTS: McCulloch Architects Ltd
QUANTITY SURVEYOR: Southern Quantity Surveyors
ENGINEER: MWH New Zealand Ltd
REFEREES:
David Main
Southern Quantity Surveyors
John McCulloch
McCulloch Architects
Dave Inwood
Milford Sound Development Authority